NEW QUESTION 10
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.

  • A. 76 hours
  • B. 78 hours
  • C. 70 hours
  • D. 60 hours

Answer: B

 

NEW QUESTION 11
A production Supervisor has noticed that Work Orders created manually are overwritten by the plan runs executed by Planning Central. After discussing this issue with the Planner, two actions are recommended to prevent the Work Orders from being overwritten by plan runs.
Identify the two recommendations.

  • A. Update Firm flag in the Details region of the Edit Work Definition page.
  • B. Update Supply Plan Options, Overwrite Firm Planned Orders = None.
  • C. Update Firm flag in the Details region of the Edit Work Definition Names page.
  • D. Update Firm flag in the Details region of the Edit Work Order page.

Answer: B,D

 

NEW QUESTION 12
While creating an item in Product Information Management (PIM), the following two item templates are selected in sequence and applied.
1. Template: Finished Goods (WIP = No, Customer Ordered = Yes)
2. Template: Sub-assembly (WIP = Yes, Customer Ordered = No)
Identify the Item Attribute values in the application.

  • A. WIP = No, Customer Ordered = Yes
  • B. WIP = Yes, Customer Ordered = No
  • C. WIP = Yes, Customer Ordered = Yes
  • D. WIP = No, Customer Ordered = No

Answer: A

 

NEW QUESTION 13
The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day and Night Shift.
Identify the correct sequence of steps to achieve this requirement.

  • A. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column> Enter 2 in Night Shift Column
  • B. Associate Resource R2 with Work Center WC1> Select Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.
  • C. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.
  • D. Associate Resource R2 with Work Center WC1> Select the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column > Enter 2 in Night Shift Column.

Answer: D

 

NEW QUESTION 14
Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.

  • A. Set the nonstocked item to be back-to-back enabled in Product Information Management (PIM).
  • B. Set a local sourcing rule in GOP to determine supply creation option as Make.
  • C. Create Supply Chain Orchestration Supply Execution Document Creation Rule for the nonstocked item.
  • D. Create Supply Order Orchestration Defaulting and Enrichment Rule for the nonstocked item.
  • E. Set the global sourcing rule in GOP to determine supply creation option as Make.

Answer: A,E

 

NEW QUESTION 15
Identify two reports that provide work order cost-related information to the costing user.

  • A. Work order Operational Analysis
  • B. Cost Accounting Dashboard
  • C. WIP Balance by Plant
  • D. Purchase Variance Summary

Answer: A,B

 

NEW QUESTION 16
Identify the three sources from which supply chain orchestration (SCO) can create the work orders.

  • A. Procurement
  • B. Quality
  • C. Planning
  • D. Order Management
  • E. Inventory Min-Max Planning

Answer: A,C,D

 

NEW QUESTION 17
Your customer has completed the required setup steps for automatic work definition. Identify the option that shows the navigation steps needed to create an automatic work definition.

  • A. Product Management> Product Information Management> Items> Edit Item > Actions> Create automatic work definition
  • B. Manufacturing > Work Definition> Manage Work Definitions> Actions> Create automatic work definition
  • C. Manufacturing> Work Definition> Manage Standard Operations> Select default standard operation> Actions> Create automatic work definition
  • D. Manufacturing > Work Definition> Manage Standard Operations> Create automatic definition

Answer: C

 

NEW QUESTION 18
In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.

  • A. Publish cost planning scenario to Accounting.
  • B. Build cost planning scenario and perform cost roll up.
  • C. Define a cost planning scenario with Material, Resource, Overhead cost plans, and work definition.
  • D. Transfer Transactions from Inventory to Costing.
  • E. Create Accounting Distributions.
  • F. Transfer transactions from production to Costing.

Answer: C,D,E

 

NEW QUESTION 19
You want to use a predefined Standard Operation in a Work Definition, but you also want to change the usage of the Standard Operation resource. Identify the setup required.

  • A. Use the Transfer and Edit Standard Operation functionality to edit the resource usage.
  • B. Use a Resource exception for the resource and alter its usage.
  • C. Select the Referenced check box while adding the standard operation to the work definition and change the usage manually.
  • D. Deselect the Referenced check box while adding the standard operation to the work definition and change the usage manually.

Answer: C

 

NEW QUESTION 20
A Work Center created a month ago is no longer in use now. You want to remove the Work Center; however, the system is no allowing you to delete it.
Identify three reasons for this.

  • A. There are resources associated with the Work Center.
  • B. The work center is being referenced in the Work Area.
  • C. The Work Center is being referenced in the Closed Work Order.
  • D. The Work Center is being referenced in the Open Work Order.
  • E. The work center is being references in the work definition operation.

Answer: A,B,D

 

NEW QUESTION 21
Work order costs are computed based on material and resource transactions reported and the cost method of the product. In a manufacturing plant, the production operator has completed a work order WO-001 ensuring proper materials and resource transactions. The materials are costed and resources are defined with rates.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.

  • A. Transfer Transactions from Production to Costing
  • B. Create accounting
  • C. Transfer Transactions from Inventory to Costing
  • D. Transfer Costs to Cost Management

Answer: A

 

NEW QUESTION 22
Identify three types of Item Quantities displayed in the Work Order History tab.

  • A. Total Quantity
  • B. Scrapped Quantity
  • C. In Process Quantity
  • D. Remaining Quantity
  • E. Completed Quantity

Answer: B,D,E

 

NEW QUESTION 23
During a Manufacturing Cloud implementation, the customer request to develop Oracle Transactional Business Intelligence reports that are not available out-of- the box.
Identify the tool that is available to the Report Developer in Manufacturing Cloud to develop the reports.

  • A. Oracle Business Intelligence Application
  • B. Oracle Business Intelligence Standard Edition
  • C. Oracle Business Intelligence Enterprise Edition
  • D. Oracle Business Intelligence Publisher

Answer: D

 

NEW QUESTION 24
To reduce the subassembly stock with no impact on material planning of child components of the subassemblies stock, you need to modify the multilevel item structure of a product.
Identify the action that meets this requirement.

  • A. Change the Supply Type = Assembly Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
  • B. Change the Supply Type = Operation Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
  • C. Change the Supply Type = Phantom in Item definition and Work Definition, for subassemblies having high inventory stock.
  • D. Change the Supply Type = Push in Item definition and Work Definition, for subassemblies having high inventory stock.

Answer: A

 

NEW QUESTION 25
You are reviewing the production status of your manufacturing plant shop floor as a production supervisor.
Your production manager wants a report on a work order status which is reserved against a particular customer. The final assembly of the work order is serialized.
Which option shows the steps to complete the task using the mobile application?

  • A. Select the infotile Customer to open the work order details page> Click Actions and select the E-mail icon> Select required work orders>Select the e-mail client, enter the recipient's e-mail, and click Send.
  • B. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode to open the work order details page > Click Actions and select the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, and click Send.
  • C. Search the work order by customer name to open the work order details page> Click Actions and select the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, and click Send.
  • D. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode to open the work order details page> Select required work orders> Click Social icon (OSN) > Select recipient, and click Share.

Answer: B

 

NEW QUESTION 26
A production Operator is executing work order in your plant. After completing move transactions, he notices that he has performed some incorrect move operations, including incorrect scrap and reject transactions. He is required to perform a reverse transaction to correct the errors. The operations are not count point enabled and not auto charged.
Identify the four transactions to correct this situation.

  • A. Reverse from reject to ready.
  • B. Reverse the product at the last operation.
  • C. Reverse from scrap to ready.
  • D. Reverse resources charged to a work order.
  • E. Reverse at an operation.
  • F. Reverse material issued to a work order.

Answer: A,C,D,F

 

NEW QUESTION 27
Your customer plans to use Oracle Representational State Transfer (REST) API with Oracle Supply Chain Management Cloud (Oracle SCM Cloud) to support integration requirements.
Identify four REST resources and the corresponding HTTP action available with Manufacturing Cloud.

  • A. Work Order Status POST method
  • B. Work Orders PATCH method
  • C. Resource transaction GET method
  • D. Resource transaction POST method
  • E. Work Orders GET method
  • F. Work Order Status GET method

Answer: B,D,E,F

 