NEW QUESTION 13
How do you gain access to the SAP Activate Methodology Jam site?
- A. Join SAP S/4HANA group on SAP Community Network
- B. Register on SAP Service Marketplace
- C. Submit e-mail address via online form
- D. Send e-mail to SAP contact address
Answer: C
NEW QUESTION 14
In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer.
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: D
NEW QUESTION 15
What can you do with Guided Configuration?
- A. Test your configured business processes
- B. Evaluate activated business processes and country versions
- C. Initial configuration of your solution and recording of updates for continuous innovation
- D. Data migration
- E. System conversion
Answer: A,B,C,D
NEW QUESTION 16
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the answer.
- A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
- B. Relative estimate in ideal person days that reflects the best estimate provided by the project team
- C. Product Owner's relative estimate of the effort that will be needed to implement the user story
- D. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
Answer: C
NEW QUESTION 17
What are some extension item types can be transported from the Quality system to the Production system?
- A. Master Data
- B. Communication Arrangements
- C. Query Designer Report
- D. Custom Fields
- E. Employee Data
- F. Form Templates
- G. Custom Business Logic
Answer: C,D,F,G
NEW QUESTION 18
In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the answer.
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: A
NEW QUESTION 19
In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: D
NEW QUESTION 20
What capabilities does SAP API Business Hub provide to help you select integration options for your project? Note: There are 3 correct Answers to this question.
- A. Sandbox for testing APIs
- B. Pre-packaged integrations
- C. Integration with IDE and code generation
- D. Advice on selecting scope items in SAP Best Practices Explorer
- E. Recommendations on using integration bus (SAP Process Orchestration or SAP Integration Suite)
Answer: A,B,E
NEW QUESTION 21
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape?
There are 2 answers to this question.
- A. P-system
- B. DEV
- C. Starter system
- D. QAS
Answer: B,D
NEW QUESTION 22
Custom Code Management process in SAP Solution Manager provides which of the following capabilities?
- A. Identify custom code and collect its usage statistics
- B. Define KPIs and report on CCM data
- C. Perform static code checks integrated into ABAP Development Tools on security, performance and syntax Replace custom developments with standard functions without necessity of a business process redesign and dedicated project
- D. Retire unused/obsolete custom code objects
Answer: A,B,D
NEW QUESTION 23
What are some of the key characteristics of the implementation approach in the SAP Activate methodology? Note: There are 2 correct Answers to this question.
- A. Fixed scope
- B. Cloud ready
- C. Based on ready-to-use content
- D. On premise only
Answer: B,C
NEW QUESTION 24
Which of the following is not about Fit/Gap Analysis (done during Explore Phase)? There are 2 answers to this question.
- A. Validate pre-activate and pre-assembled solution in the development system.
- B. Drive towards adopting customers processes.
- C. Minimize the needs for rework during realization.
- D. Prioritize delta requirement and gaps.
Answer: A,B
NEW QUESTION 25
Selective Data Transition covers the migration of relevant business data from SAP ERP to SAP S/4HANA.
It allows a tailored scope between System Conversion and New Implementation with the flexibility to adapt data and processes in one transition step.
- A. True
- B. False
Answer: A
NEW QUESTION 26
Which enhancements to SAP Cloud ALM are planned for the future? Note: There are 2 answers to this question.
- A. Functional scope
- B. Task coverage
- C. Process scope
- D. Product coverage
Answer: A,D
NEW QUESTION 27
What are some characteristics of SAP S/4HANA Cloud?
- A. SAP S/4HANA Cloud includes quarterly innovation cycles.
- B. SAP S/4HANA Cloud provides additional functionality for customers that require broad extensions and deep configuration capabilities.
- C. SAP S/4HANA Cloud runs in an infrastructure with private, managed services for SAP solutions.
- D. SAP S/4HANA Cloud is multi-tenant, meaning your service runs in a shared environment.
- E. SAP S/4HANA Cloud is single-tenant; meaning your service runs in a dedicated environment.
Answer: A,D
NEW QUESTION 28
Which of the following belong to the Application Design and Configuration workstream for SAP S/4HANA Cloud in the Explore phase? Note: There are 2 correct Answers to this question.
- A. Kick-off workshop
- B. Configuration definition
- C. Integration prerequisites confirmation
- D. Fit-to-standard workshop
Answer: B,D
NEW QUESTION 29
Where can you find Integration Content? 3 correct answers
- A. SAP Cloud Appliance Library
- B. SAP API Business Hub
- C. SAP Best Practice Explorer
- D. SAP Solution Manager
- E. Cloud Integration Automation service
Answer: B,C,E
NEW QUESTION 30
......
SAP Exam Practice Test To Gain Brilliante Result: https://www.itpass4sure.com/E_ACTCLD_21-practice-exam.html